Your solar was installed but never switched on

Panels on the roof but no Permission to Operate from NV Energy? Where the approval chain stopped, how to check each step yourself, and who can finish it.

Checked on 2026-09-285 min read6 sources
A new rooftop solar array in bright midday sun on a Las Vegas stucco house, the meter and disconnects at the side of the house in deep shade

Panels on the roof do not mean a working system. Until NV Energy issues Permission to Operate, your system may not be switched on and earns no credit on your bill. If yours was installed and never turned on, the approval chain stopped somewhere, and every step in it leaves a record you can check today. Finishing it does not need the original installer.

What Permission to Operate is

NV Energy's Net Metering and Energy Storage Interconnection Handbook, in the revision dated 10/16/2025, defines Permission to Operate as "the formal authorization granted by NV Energy to interconnect the net metering system and begin operating the generator in parallel with the electrical grid."

Two lines in the same handbook explain why it matters so much:

  • Systems "may not be energized prior to successful final verification by NV Energy."
  • The customer "will not receive kWh credit for energy put back into the grid until the NV Energy meter(s) is set."

So a finished looking array without that approval is, for billing purposes, not there.

The chain, and where it usually stops

The handbook sets out the steps in order. Knowing them tells you what question to ask.

StepWhat happensWhat it leaves behind
1. ApplicationFiled in NV Energy's portal, PowerClerk. Incomplete until the $189 Southern Nevada fee is paid.An application number
2. First reviewApplication review within ten business days, plus engineering or metering review if needed.Approval, or a corrections notice
3. Installation and permitThe system is built and the city or county inspects it.A permit with a passed final inspection
4. Final documentsThe installer uploads the building permit, the final inspection card and the signed interconnection agreement.A signed agreement
5. Second review and inspectionNV Energy reviews the documents and sends a technician to inspect and set the meters, within the second ten business days.New meter on the wall
6. Permission to OperateOnce the inspection passes and the meters are set, an email goes to all relevant parties.The email, and a net metering rate on your bill

The places it breaks are predictable.

The application was sent back and nobody answered. The handbook says if corrections are not submitted by the 60 calendar day deadline, the application is cancelled due to inactivity.

The permit was never finalled. NV Energy cannot finish without the final inspection card from the city or county. The City of Las Vegas residential solar permit guidance lists a single inspection for photovoltaic, the #227 inspection, scheduled online.

The paperwork was never finished. The handbook gives a project one year in the Awaiting Documentation status to submit all final documentation.

The utility inspection failed. If NV Energy's technician finds an issue, the project moves to a corrections status and is re-inspected once it is fixed.

The system was sized too large. Application review confirms the system is not designed to produce more than 100 percent of the home's annual energy needs, under NRS 704.771, using the largest 12 consecutive months of usage within the past 24. KTNV reported on September 10 2025 on a Las Vegas homeowner whose rooftop system was installed but not generating six months after his contract began, with his loan payments already running, after the application stalled on exactly this sizing question.

How to find out where yours stopped

You can do most of this in an evening.

  1. Search your email for a Permission to Operate notice. It goes to all relevant parties, which should include you. If you have one, the problem is not approval; see how to find out if your system still works.
  2. Read your NV Energy bill. The handbook says your account is placed on the applicable net metering rate after Permission to Operate. How to read your NV Energy bill once you have solar shows where the rate and the export lines sit.
  3. Look up the permit. Search your address on the permit portal for your city, or on Clark County's Citizen Access Portal if you are in unincorporated county. You want the solar permit and whether its final inspection passed. Solar permits in Las Vegas covers which desk your address falls under.
  4. Get the NV Energy application number. Ask the installer for it and its status in writing. If the installer does not answer, NV Energy's clean energy team is listed in the handbook at cleanenergy@nvenergy.com and 866-786-3823. Have the account holder make the call, because the handbook requires the host customer name to match the NV Energy account.

Why it matters beyond the bill

Two things keep running while the system sits idle.

Your payments. A loan or lease is a separate contract with a finance company. In the case KTNV reported, the loan payments had started while the system sat unused. Read the payment terms in your agreement, and if payments started before the system worked, raise it with the finance company in writing.

Some warranty clocks. For at least one maker, the clock is tied to this approval. The Enphase Energy System Limited Warranty for the US and Canada, updated September 27 2023, defines a product as "activated" when the solar system has received permission to operate from the authorities having jurisdiction. Check what your own equipment warranties say about their start date.

Who can finish it

Anyone properly licensed, not only the company that started it.

NV Energy's handbook requires interconnections to be performed by a Nevada licensed C-2 or C-2g electrical contractor, and says the permit inspection will not be conducted if the contractor's licence is expired, suspended or revoked. That last point matters if your installer has since lost its licence: a new licensed contractor may need to take over the permit.

Before you hire anyone, check the licence and its status on the Nevada State Contractors Board search page. If the company that installed your system has closed, your solar company went out of business covers the rest: what survives, what does not, and the recovery fund.

What a licensed contractor can do here is concrete: find the application and its status, correct and resubmit it, close the permit, fix any inspection item, and see it through to the meter set. We take on systems other companies started, and we will tell you in writing what is left to do before we quote it.

Questions people ask us

What does Permission to Operate mean for solar in Las Vegas?

It is NV Energy's formal authorisation to connect your system and run it alongside the grid. NV Energy's Net Metering and Energy Storage Interconnection Handbook, revision dated 10/16/2025, says a Permission to Operate email goes to all relevant parties once the utility inspection passes and the required meters are set. Until then the system may not be energized.

My panels were installed months ago. Why are they not on?

Something in the chain stopped. The usual places are an application that was never filed or was sent back for corrections, a building permit that was never given a final inspection, an interconnection agreement that was never signed, or a utility inspection that found a problem. Each of those leaves a record you or a contractor can look up.

Do I get credit for power my system makes before Permission to Operate?

No. NV Energy's handbook says the customer will not receive kilowatt hour credit for energy put back into the grid until the NV Energy meter is set, and that systems may not be energized before NV Energy's final verification. Switching it on yourself early is not allowed and earns nothing on your bill.

How long does NV Energy take to approve a solar system?

The handbook describes two review windows of ten business days each. The first covers application review, and any engineering or metering review. The second covers the final documentation review and the utility inspection. Corrections restart the relevant review, and an application with corrections outstanding for 60 calendar days is cancelled.

Who do I call if my system was never switched on?

Start with whoever installed it and ask for the application number and its status. If they do not answer, NV Energy's clean energy team is reachable at cleanenergy@nvenergy.com or 866-786-3823, according to its handbook. Finishing the work needs a Nevada licensed C-2 or C-2g electrical contractor, which does not have to be the original installer.

Why would NV Energy reject a solar application?

One reason is size. NV Energy's handbook says application review confirms the system is not designed to produce more than 100 percent of your annual energy needs, under NRS 704.771, using your largest 12 consecutive months of usage within the past 24. KTNV reported in September 2025 on a Las Vegas homeowner whose installed system sat unused over exactly this question.

Where these numbers come from

  1. NV Energy, Net Metering and Energy Storage Interconnection Handbook, revision dated 10/16/2025 (Permission to Operate definition, PowerClerk application and the $189 Southern Nevada fee, the two ten business day review windows, 60 day correction deadline, one year to submit final documentation, final inspection card and interconnection agreement, meter set and Permission to Operate email, no energizing before final verification and no kWh credit until the meter is set, NRS 704.771 sizing check, clean energy contact details) checked 2026-09-28
  2. KTNV, Las Vegas homeowner says he's stuck paying for a solar system he can't use, by Geneva Zoltek, published 2025-09-10 checked 2026-09-28
  3. City of Las Vegas Building and Safety, Residential Photovoltaic (Solar) Permits, effective February 15 2024, updated 05/29/2024 (online permit, the single #227 inspection for photovoltaic, scheduling inspections online) checked 2026-09-28
  4. Clark County Building & Fire Prevention, Citizen Access Portal page checked 2026-09-28
  5. Enphase Energy, Inc., Enphase Energy System Limited Warranty, United States, United States Territories and Canada, updated September 27 2023 (activation date defined by permission to operate) checked 2026-09-28
  6. Nevada State Contractors Board, Residential Solar resource page, including the licence search and complaint routes checked 2026-09-28
Not affiliated

Simmons Solar Electric is not affiliated with, authorised by, or acting for any company named on this page, or for its trustee or estate. We do not honour another company's workmanship warranty. Everything stated here about a company is public record, with its source listed below.

We recheck this page quarterly. Last checked 2026-09-28. If a number here has moved, tell us and we will fix it the same week.

Solar Rescue

Get your system looked at by a licensed electrician.

We inspect what is on your roof, test what is still working, and tell you in writing what it needs. You keep the report whether or not you hire us.

(725) 248-0578

Licensed Nevada contractor NSCB 0032580A. No obligation, and no visit until you ask for one.

Get your free quote

No cost, no obligation, no high-pressure pitch. If your roof is not a good candidate we will say so.

We usually reply the same business day. Prefer to talk? Call (725) 248-0578. Any contract you sign with us carries Nevada's cover page and cancellation right: three business days, ten if you are 60 or older. Actual utility rates may go up or down and actual savings may vary.

Thanks. We got it and will call you shortly, usually within the hour during business hours.